Projects
Completed
Stalowa Wola, PL
2022
Unloading and anchoring of the Heller CP8000 machine tool Scope of work: - unloading of the machine tool outside the facility with the help of a crane and fork lift truck - transportation on rollers to the target destination in the…
SeeCompleted
Siemianowice Śląskie, Poland
2022
Our company undertook the dismantling of the entire process line of the Tube Rolling Mill, which will again be reconstructed 1:1 in Oman. - Dismantling consists of a comprehensive service of disconnecting, dismantling, sorting seamless tube…
SeeCompleted
Brilon- Szydłowiec / DE-PL
2021
The work included: Brilon: - Dismantling of machining centres, shrink-wrapping and preparation for transport. Szydłowiec: - Implementation of machine assembly including geometry.
SeeCompleted
Starachowice, POLAND
2021
- Mechanical, electrical and pneumatic assembly service for pilot line components - rework area including fabrication, supply and installation of structures and tanks, - ancillary works, i.e. modification of equipment such as belt conveyors,…
SeeCompleted
Opoczno, POLAND
2021
Scope of work carried out: Mechanical installation of the press on the foundation Installation of the hydraulic unit Cooling system installation Electrical assembly of the press Mechanical assembly of tunnel and horizontal dryers…
SeeCompleted
CONSTRUCTION OF FOUNDATIONS FOR THE BORING MACHINE
Fundamenty pod wytaczarkę
Construction of foundations by Blachmix for the boring machine
SeeCompleted
SZCZECIN TRAMS, POLAND
Installation and commissioning of new Pinacho SC 325x2000 mm lathe
SeeCompleted
Croatia
2019
Disassembly, loading and shipment to China of the SKODA W 250 boring machine
See