Projects
Completed
Stalowa Wola, PL
2022
Unloading and anchoring the Heller machine tool Scope of work: - unloading the machine tool outside the hall with the use of a crane and a forklift - transport on rollers to the destination place in the hall - anchoring the machine on the…
SeeCompleted
Cracow, PL
2022
Postforming sequence disassembly Scope of work: Disconnecting machines from utilities. Electrical disassembly, disassembly of machines. Mechanical disassembly of disassembled machine elements and line elements. Description and…
SeeCompleted
Neitersen- Tarnowskie Góry / DE-PL
2022
Relocation of machines from Germany to Poland. We also took care of the foundation for the machine tools.
SeeCompleted
Stalowa Wola, PL
2022
Unloading and anchoring of the Heller CP8000 machine tool Scope of work: - unloading of the machine tool outside the facility with the help of a crane and fork lift truck - transportation on rollers to the target destination in the…
SeeCompleted
Siemianowice Śląskie, Poland
2022
Our company undertook the dismantling of the entire process line of the Tube Rolling Mill, which will again be reconstructed 1:1 in Oman. - Dismantling consists of a comprehensive service of disconnecting, dismantling, sorting seamless tube…
SeeCompleted
Brilon- Szydłowiec / DE-PL
2021
The work included: Brilon: - Dismantling of machining centres, shrink-wrapping and preparation for transport. Szydłowiec: - Implementation of machine assembly including geometry.
SeeCompleted
Starachowice, POLAND
2021
- Mechanical, electrical and pneumatic assembly service for pilot line components - rework area including fabrication, supply and installation of structures and tanks, - ancillary works, i.e. modification of equipment such as belt conveyors,…
SeeCompleted
Opoczno, POLAND
2021
Scope of work carried out: Mechanical installation of the press on the foundation Installation of the hydraulic unit Cooling system installation Electrical assembly of the press Mechanical assembly of tunnel and horizontal dryers…
See